Timeline

– 3 August 2014 – Land Reserved

– 5 August 2014 – Land Holding deposit

– 17 August 2014 – Land Contracts Signed

– 29 August 2014 – Commencement Deposit to Masterton

– 3 September 2014 – 5% Land Deposit Paid and Contracts Signed

– 26 September 2014 – Land given to Council for Registration

-13 October 2014 – Masterton’s Surveyor attends site

– 27 October 2014 – Land Registered

– 6 November 2014 – DP Paperwork and 88B received

– 10 November 2014 – LAND SETTLEMENT

– 16 November 2014 – First Plans

– 9 December 2014 – Correct plans

– 12 December 2014 – Contracts and 5% Deposit – 90 Days to Construction Starts

(not including M’s 27 Day holiday period)

– 18 December 2014 – All Appointments for Internal Selections Booked

– 16 January 2015 – Ark Finishing Touches Appointment – Screen Doors and Shutters

– 20 January 2015 – Plans sent to the Estate for Approval against Design Guidelines

– 23 January 2015 – Don’s Tiles and Accent Flooring Appointment

– 27 January 2015 – Artline Kitchens Appointment

– 2 February 2015 – Colours Appointment

– 4 February 2015 – Mulgoa Rise Approval of Plans and file sent off by M for Council Development Approval (DA)

– 10 February 2015 – DA Number Allocated

– 11 February 2015 – Electrical Appointment Date Confirmed

– 19 February 2015 – Electrical Appointment Completed

– 2 March 2015 – Consultation period of the DA process finishes

– 9 March 2015 – Issues Letter Received from council DA Assessor

– 11 March 2015 – Masterton response to council issues letter

– 17 March 2015 – Further issues letter from council relating to the fill and DEB. Contour Survey and updating of plans ordered by Masterton

– 25 March 2015 – Contour Survey received by Masterton. Plans back in drafting

– 27 March 2015 – Plans back with council for approval

– 9 April 2015 – DA Approval

– 13 April 2015 – Confirmation that the Peg Out is Ordered

– 14 April 2015 – DA documents sent to Certifier for Construction Certificate requirements

– 15 April 2015 – Certifier confirmed infastructure restoration bond is all that is required for the construction certificate

– 17 April 2015 – Peg Out Completed

– 21 April 2015 – Peg Out Report received by Masterton and Construction Certificate Lodged. PCV relating to DA Approval updated

– 29 April 2015 – Construction Plans Received this afternoon although are incorrect

– 1 May 2015 – Validation completed and Construction Plans Signed

– 29 May 2015 – Moved to Construction Planning Stage

-4 June 2015 – 20 Day Countdown has officially started with Commencement Letter from our bank

– 15 June 2015 – Site fenced off

-26 June 2015 – Excavation

– 7 July 2015 – Piers and Slab formwork

– 8 July 2015 – Slab plumbing and waffle pods delivered

– 9 July 2015 – Waffle Pods and mesh installed

– 11 July 2015 – SLAB completed

– 13 July 2015 – 1st Progress Claim

– 16 July 2015 – Electrical Cables laid 

– 21 July 2015 – Plumbing Trenches Dug

– 22 July 2015 – Drainage Plumbing Completed 

– 23 July 2015 – Bottom Story Frames Delivered

– 30 July 2015 – Frames for ground floor started

– 11 August 2015 – Frames for second story started

– 20 August 2015 – lower roof trusses completed, commons bricks delivered 

– 21 August 2015 – Balcony installed

– 22 August 2015 – Bricks Started

– 24 August 2015 – Electrical Box Installed and Internal Plumbing Started

– 25 August 2015 – Gas Connected and Pest Control Installed 

– 31 August 2015 – Frames Progress Claim received 

– 4 September 2015 – Ground Floor Bricks Completed. Waiting for scaffolding for second story 

– 9 September 2015 – Scaffold started

– 10 September 2015 – Staircase measured up

– 17 September 2015 – Second Story Bricks started

– 22 September 2015 – Second Story Bricks Completed

– 28 September 2015 – Roof Trusses Complete

– 12 October 2015 – Upper level gutters, facia and barge trim complete

– 15 October 2015 – Main Roof completed 

– 23 October 2015 – pre work for the facade rendering 

– 26 October 2015 – Render started

– 2 November 2015 – Render Complete 

– 13 November 2015 – Eaves delivered

– 16 November 2015 – New site supervisor starts as original one resigns without notice to us

– 18 November 2015 – Eaves and cladding started

– 11 December 2015 – Brick Clean 

– 16 December 2015 – Dons Tiles confirms tiles are ordered today

– 18 December 2015 – carpenter does balcony finishes and footings for vanity

– 16 January 2016 – carpenter fixes all loose noggins and sands upstairs floor

– 20 January 2016 – Cladding to top Gable Sets and Eave boxing 

– 29 January 2016 – eaves, down pipes and cladding painted 

– 5 February 2016 – some fixes to the poor plumbing and carpentry. Cladding to top of house complete 

– 12 February 2016 – Electrical Rough in and Pillar Render painted

– 15 February 2016 – most of the scaffold taken down

– 22 February 2016 – lower roof gutters and barge installed

– 23 February 2016 – Ducting for air con installed

– 24 February 2016 – final acid wash on bricks

– 26 February 2016 – lower roof materials delivered

– 1 March 2016 – insulation installed, gyprock delivered

– 2 March 2016 – Gyprock started

– 6 March 2016 – lower roof completed 

– 9 March 2016 – Antenna installed

– 11 March 2016 – Internal Gyprock complete

– 12 March 2016 – Cornices started

– 14 March 2016 – Gyprock sanded

– 15 March 2016 – Cornices complete and stairs installed 

– 16 March 2016 – kitchen cupboards installed, vanities delivered, waterproofing completed

– 17 March 2016 – water tank installed

– 18 March 2016 – Internal Doors, frames, architraves delivered. LOCK UP

– 22 March 2016 – Broken window in great room fixed

– 24 March 2016 -ensuite bathtub delivered. Internal doors installed. Door Frames started. 

– 29 March 2016 – Windows/Door Frames, architraves, and bedroom robe doors installed.

– 30 March 2016 – vanities installed. Sentinel fit out started. 

– 31 March 2016 – TV and Data points cut out. Lower eaves and cladding started

– 1 April 2016 – lower eaves and cladding completed. Top gable eaves fixed

– 7 April 2016 – top gable metal work fixed, window fixed

– 8 April 2016 – tiles delivered and screeds completed 

– 9 April 2016 – Tiles started

– 12 April 2016 – Tiles continue, kitchen island bench fixed

– 18 April 2016 – internal painting started

– 19 April 2016 – stone benchtops installed (except kitchen waterfall edges), bathroom vanities and kitchen sink installed 

– 23 April 2016 – Balcony Tiles complete, powder room grouted

– 27 April 2016 – Laundry robes installed, wood work on stairwell and window installed 

– 29 April 2016 – Patch and Sanding of woodwork for next coat of paint

– 3 May 2016 – Hills Hub Installed

– 4 May 2016 – bathroom wall tiles competed and gyprock completed along with wall imperfection fixes 

– 5 May 2016 – walls and floors sanded. Balcony door fixed

– 11 May 2016 – painters identifying fixes and filling more imperfections

– 16 May 2016 – Balcony Installed, internal painting continues

– 17 May 2016 – front down pipe fitted

– 18 May 2016 – sensor light positions fixed by electrician, external paint continues

– 23 May 2016 – Render fixed

– 25 May 2016 – Air Con Fitted, down stairs floor tiles laid, lower downpipes painted

– 26 May 2016 – main floor tiles grouted, balcony tiles fixed, smart floor tile wastes laid

– 27 May 2016 – one roller door installed, painting touch ups

– 28 May 2016 – render paint touch ups

– 30 May 2016 – Scaffold Down

– 31 May 2016 – taps, toilets and tubs installed

– 2 June 2016 – Our building inspector conducts his walk through

– 3 June 2016 -PowerPoints for the garage doors fixed, Carpenter commences door furniture installation

– 6 June 2016 – bathtub surround in ensuite fixed 

– 7 June 2016 – bathtub surround waterproofed. Second Garage door delivered 

– 8 June 2016 – more door handles installed. Carpenter on site

– 5 July 2016 – PCI

– 7 July 2016 – Painters 

– 13 July 2016 – doorstops installed and kitchen and mirrors to be fixed on order

– 14 July 2016 – Certifier report received with actions to be completed for IOC

– 15 July 2016 – construction fence and porta loo removed

– 18 July 2016 – laundry and study installed

– 22 July 2016 – carpet installed

– 25 July 2016 – final walk through

– 28 July 2016 -KEYS

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s